Custom OEM Protective Cases: Realistic Timeline From RFQ to Shipment

Direct answer

For an injection-molded OEM case, expect about 45 days from confirmed drawing to shipment when the factory already has a suitable mold, and about 125 days when new tooling must be cut — tooling and first-article validation dominate the second figure. Color, foam, hardware and print customization happen in parallel and rarely extend the schedule if specified early.

§01Stage-by-stage

StageExisting moldNew moldWhat happens
RFQ & drawing freezeweek 0week 03D/2D confirmed, resin, color, hardware locked
Toolingweeks 1–10mold design, steel cutting, fitting
T1 samplesweek 1weeks 11–13first shots; wall, warp and gloss checked
Validationweeks 1–3weeks 13–15sealing/drop checks, foam fit, corrections (T2 if needed)
Mass productionweeks 3–5weeks 15–16molding, assembly, foam CNC, QC
Shipment (EXW/FOB)≈day 45≈day 125packing, inspection, handover

§02What shortens or lengthens the schedule

Planning tip: put inspection rights (third-party or remote video) and a T1 sample approval gate in the purchase contract. The T1 gate is where 90 % of OEM disappointments are preventable.

REF KB-OEM-010 · Published 2026-09-21 · Reviewed by the KeXin Materials engineering team · Sources: IEC 60529; ISO 6346; ATA 300; MIL-STD-810; Incoterms® 2020